Construction progress

The readiness of each block is updated at the end of every month. You are welcome to come and see the site for yourself.

Block by block

As of 28 September 2026

Block A

78% complete

18 floors136 flatsFrame: 18 of 18 floorsHandover: June 2027

The frame is complete. The façade has reached the 11th floor; plastering and wiring are under way inside the flats.

Block B

46% complete

18 floors136 flatsFrame: 12 of 18 floorsHandover: December 2027

The frame has reached the 12th floor and rises by one floor every nine days. Walls are being laid on the lower floors.

Block C

9% complete

14 floors104 flatsFrame: 0 of 14 floorsHandover: September 2028

The foundation slab is poured and the walls of the underground car park are going up. The frame starts in December 2026.

Project timeline

  1. : Completed

    Building permit issued

  2. : Completed

    Foundations of Block A started

  3. : Completed

    Frame of Block B started

  4. : Completed

    Frame of Block A completed

  5. : Completed

    Show flat opened

  6. : Planned

    Block A handed over

  7. : Planned

    Block B handed over

  8. : Planned

    Block C and the courtyard handed over

Reports from the site

  1. Façade works on Block A: protective mesh and a hoist

    28 September 2026 · Block A

    The façade has reached the 11th floor

    Porcelain panels are fixed up to the 11th floor on the street side and the 8th on the courtyard side. Windows are fully fitted on floors 2 to 9.

  2. The reinforced-concrete frame of Block B

    24 September 2026 · Block B

    The 12th floor of the frame is poured

    186 m³ of concrete went into the 12th-floor slab. Samples from the columns and the slab were tested by an independent laboratory and confirmed class B30.

  3. The foundation pit of Block C with its rebar mesh

    17 September 2026 · Block C

    Walls of the underground car park are going up

    With the foundation slab done, work has moved to the walls of level −2: 60% of the perimeter is poured and two layers of waterproofing are going on.

  4. Engineers measuring a window opening inside a flat

    26 August 2026 · Block A

    Plastering and wiring inside the flats

    Walls are plastered and wiring is run on floors 2 to 12. Two of the lifts are installed and working in construction mode.

  5. Workers tying column rebar on a floor slab

    20 August 2026 · Block B

    Walls are being laid on the lower floors

    With the frame at the 10th floor, aerated-concrete walls have started on floors 2 to 5. Two crews work in shifts.

  6. A worker on the rebar of the foundation slab

    30 July 2026 · Block C

    The foundation slab is poured

    2,900 m³ of concrete went into the 1.4-metre slab in a single 38-hour pour. The slab holds 410 tonnes of rebar.

  7. A tower crane and a block with its frame going up

    18 June 2026 · Block A

    The frame is complete

    The 18th-floor slab and the roof slab are poured. The tower crane comes down in July and façade hoists take its place.

Visit the site

A manager takes you into the block, in a helmet and vest, to the floor you want to see. Visits run every day, by appointment.