2,400 tonnes of structures for a 38,000 m² warehouse: 23 weeks from shop drawings to supervised erection.

The steel frame of a building under construction

The customer came to us with the architectural design. Our design office produced the shop drawings in 6 weeks: welded beams spanning 36 metres, 12-⁠metre columns and runways for 5-⁠tonne underslung cranes. The structure was fabricated to EXC2 and hot-⁠dip galvanised.

Sumgait to Alat is 94 km. Murov Logistics made 131 runs over 14 weeks; the long beams travelled at night under escort. The customer’s contractor erected the frame, with two of our engineers on site checking bolt tension and geometry.