A 30 MW solar plant in Gobustan
410 km of cable and 1,150 tonnes of galvanised mounting structure for the panels, in 16 weeks.

Two of our plants worked on the station at once: Murov Kabel made the low-voltage and 35 kV medium-voltage cable, Murov Metal the mounting profiles and pile caps. The customer dealt with one contract, one schedule and one person in charge.
The mounting profiles were rolled from Z275 galvanised strip because the soil on site is saline. Holes were punched on the line, so nothing had to be drilled on site.