Sumgait · Onshore
Compressor package set in Sumgait
The package was moved at night and set on its foundation in a tandem lift
- Client
- A gas transmission operator
- Period
- September 2023 – October 2023 (2 months)
- Most people on site in a day
- 14
- Man-hours
- 4,100
- Lost-time injuries
- 0

The brief
A gas transmission operator asked us to bring a 112-tonne compressor package from the port to its station in Sumgait and set it on its foundation.
In figures
- package weight
- 112t
- moved at night
- 46km
- in the tandem lift
- 2cranes
How the work went
- We surveyed the route, had the load limits of two bridges confirmed and agreed the night move with the road police.
- The package travelled 46 km on our lowbed at night.
- A tandem lift plan kept both cranes below 80% of their capacity.
Result
The package arrived overnight and was on its foundation the next day.
One company answered for every step from transport to the lift, and that saved us a lot of time.
The station’s construction manager
Services
Equipment used



Trailer · 53.7 t
Goldhofer STZ-VP 3-42/80 + MAN TGS 33.480
Lökbatan yard · ×2
- with operator
- ₼1,300 / day
Other projects

Sangachal · 2025 · Onshore
Pump skids built and set in Sangachal
Cranes and heavy lifting, fabrication and welding
3 skids fabricated and tested

Alat · 2022 · Nearshore
Trestle repair at Alat
Fabrication and welding, cranes and heavy lifting, corrosion protection
640 m of trestle repaired