Pump skids built and set in Sangachal

Skids assembled in Lökbatan, moved at night and set with two cranes

Client
The onshore terminal of an offshore field operator
Period
October 2025 – December 2025 (3 months)
Most people on site in a day
22
Man-hours
26,400
Lost-time injuries
0
A crane lifting a heavy load into the sky

The brief

The onshore terminal needed three new pump skids. The client wanted one contractor to fabricate and test them, move them to the terminal and set them on their foundations next to running equipment.

In figures

fabricated and tested
3skids
heaviest lift
86t
on site against 12 planned
9days

How the work went

  • The skids were assembled at our Lökbatan yard, welds inspected and the hydrotest witnessed by the client’s representative.
  • A lift plan was written for each lift and agreed through the terminal’s permit system.
  • The skids travelled on our lowbed over two nights; the heaviest, 86 t, was set with the LTM 1250-5.1.

Result

Work at the terminal took 9 days against 12 planned; the terminal did not stop for an hour.

The client’s words
An 86-⁠tonne lift next to running pumps, and we saw the plan down to the last detail beforehand.

The terminal’s maintenance manager

Services

Equipment used

Other projects

Have similar work?

Pick the service, the site and the length: the price with crew and equipment is worked out at once.

Call usMessage on WhatsAppEquipment hireRequest a quote