
Sangachal · Onshore
Pump skids built and set in Sangachal
Skids assembled in Lökbatan, moved at night and set with two cranes
- Client
- The onshore terminal of an offshore field operator
- Period
- October 2025 – December 2025 (3 months)
- Most people on site in a day
- 22
- Man-hours
- 26,400
- Lost-time injuries
- 0

The brief
The onshore terminal needed three new pump skids. The client wanted one contractor to fabricate and test them, move them to the terminal and set them on their foundations next to running equipment.
In figures
- fabricated and tested
- 3skids
- heaviest lift
- 86t
- on site against 12 planned
- 9days
How the work went
- The skids were assembled at our Lökbatan yard, welds inspected and the hydrotest witnessed by the client’s representative.
- A lift plan was written for each lift and agreed through the terminal’s permit system.
- The skids travelled on our lowbed over two nights; the heaviest, 86 t, was set with the LTM 1250-5.1.
Result
Work at the terminal took 9 days against 12 planned; the terminal did not stop for an hour.
An 86-tonne lift next to running pumps, and we saw the plan down to the last detail beforehand.
The terminal’s maintenance manager
Services
Equipment used



Trailer · 53.7 t
Goldhofer STZ-VP 3-42/80 + MAN TGS 33.480
Lökbatan yard · ×2
- with operator
- ₼1,300 / day

Welding set · 500 A
Lincoln Electric Vantage 500
Lökbatan yard · ×2
- with operator
- ₼300 / day
- without operator
- ₼95 / day
Other projects

Lökbatan yard · 2025 · Onshore
Manifolds for a gas processing unit
Fabrication and welding, inspection and NDT, corrosion protection
312 t of piping and steelwork

Sumgait · 2023 · Onshore
Compressor package set in Sumgait
Cranes and heavy lifting
112 t package weight

Alat · 2022 · Nearshore
Trestle repair at Alat
Fabrication and welding, cranes and heavy lifting, corrosion protection
640 m of trestle repaired
Have similar work?
Pick the service, the site and the length: the price with crew and equipment is worked out at once.