Lökbatan yard · Onshore

Manifolds for a gas processing unit

Spools and manifolds made, coated and tested at the yard

Client
An EPC contractor building a gas processing unit
Period
October 2024 – April 2025 (7 months)
Most people on site in a day
41
Man-hours
96,000
Lost-time injuries
0
Welding steel sections in a shop, sparks flying

The brief

An EPC contractor building a gas processing unit wanted its spools and manifolds made at a yard rather than on site, where space and time for welding were short.

In figures

of piping and steelwork
312t
hydrotested and delivered
11manifolds
ahead of the deadline
9days

How the work went

  • We drew up the material take-⁠off and welding procedures from the drawings; the client approved them.
  • Spools were welded in the shop and every weld was ultrasonically tested.
  • Finished manifolds were blasted, coated and hydrotested at the yard.
  • Each manifold was handed over with its own document file.

Result

312 t of piping and steelwork, 11 manifolds, delivered 9 days early.

The client’s words
The manifolds reached site tested and documented; all we had to do was connect them.

The EPC contractor’s construction manager

Services

Equipment used

Other projects

Have similar work?

Pick the service, the site and the length: the price with crew and equipment is worked out at once.

Call usMessage on WhatsAppEquipment hireRequest a quote