Off Pirallahi island · Nearshore
Nearshore pipeline repair at Pirallahi
A corroded section in up to 4 m of water replaced, then a 24-hour hydrotest
- Client
- An operator of a shallow-water field
- Period
- June 2025 – August 2025 (3 months)
- Most people on site in a day
- 36
- Man-hours
- 41,500
- Lost-time injuries
- 0

The brief
Part of a 12-inch line in shallow water off Pirallahi had been weakened by corrosion and carried 38 temporary clamps fitted over the years. The client wanted the whole section replaced.
In figures
- of 12-inch pipe replaced
- 2.6km
- from earlier temporary repairs removed
- 38clamps
- of work over water
- 64days
How the work went
- The line lay in up to 4 m of water: pipe was welded into strings on the shore and lowered into the water.
- Every weld was ultrasonically tested and the joints were coated.
- The crew reached the site by work boat every day; 7 days were lost to the sea, and the schedule had allowed for them.
- The new section passed a 24-hour hydrotest.
Result
2.6 km of pipe replaced in 64 days; the line came back on stream on the planned date.
Weather stand-by was in the schedule from the start, so the deadline held.
The client’s pipeline engineer
Services
Equipment used


Welding set · 200 A
Lincoln Electric Pipeliner 200D
Lökbatan yard · ×4
- with operator
- ₼285 / day
- without operator
- ₼80 / day

Compressor · 27.6 m³/min
Atlas Copco XRVS 1000
Lökbatan yard · ×2
- with operator
- ₼480 / day
- without operator
- ₼340 / day

Generator · 500 kVA
Caterpillar XQP500
Lökbatan yard · ×3
- with operator
- ₼520 / day
- without operator
- ₼380 / day
Other projects

Siyazan district · 2026 · Onshore
Flowline replacement in Siyazan
Pipelines, inspection and NDT, corrosion protection
18.4 km of 6 to 10-inch flowline replaced

Lökbatan yard · 2025 · Onshore
Manifolds for a gas processing unit
Fabrication and welding, inspection and NDT, corrosion protection
312 t of piping and steelwork

Shirvan · 2024 · Onshore
Tank blasting and coating in Shirvan
Corrosion protection, inspection and NDT
9,800 m² blasted and coated
Have similar work?
Pick the service, the site and the length: the price with crew and equipment is worked out at once.