Four tanks blasted and coated outside and on the floors, cathodic protection installed

Client
An oil storage terminal’s operator
Period
May 2024 – September 2024 (5 months)
Most people on site in a day
28
Man-hours
58,200
Lost-time injuries
0
A large steel tank with a stairway against a blue sky

The brief

Four tanks at an oil storage terminal needed new external coating and floors. The terminal wanted to take them out of service one at a time for blasting, coating and new cathodic protection.

In figures

blasted and coated
9,800m²
of coating thickness measured
2,300points
installed for cathodic protection
48anodes

How the work went

  • Tanks were emptied one by one; the terminal kept working.
  • Surfaces were abrasive-blasted and given a three-coat system.
  • Coating thickness was measured at 2,300 points and recorded.
  • Each tank got cathodic protection with 12 anodes, installed and surveyed.

Result

9,800 m² blasted and coated over 5 months; tanks went back into service one after another.

The client’s words
We handed over the tanks in turn, and the whole job finished without the terminal stopping.

The terminal’s chief engineer

Services

Equipment used

Other projects

Have similar work?

Pick the service, the site and the length: the price with crew and equipment is worked out at once.

Call usMessage on WhatsAppEquipment hireRequest a quote