Shirvan · Onshore
Four tanks blasted and coated outside and on the floors, cathodic protection installed

Four tanks at an oil storage terminal needed new external coating and floors. The terminal wanted to take them out of service one at a time for blasting, coating and new cathodic protection.
9,800 m² blasted and coated over 5 months; tanks went back into service one after another.
We handed over the tanks in turn, and the whole job finished without the terminal stopping.
The terminal’s chief engineer

Compressor · 27.6 m³/min
Lökbatan yard · ×2

Generator · 500 kVA
Lökbatan yard · ×3


Siyazan district · 2026 · Onshore
Pipelines, inspection and NDT, corrosion protection
18.4 km of 6 to 10-inch flowline replaced

Off Pirallahi island · 2025 · Nearshore
Pipelines, inspection and NDT
2.6 km of 12-inch pipe replaced

Lökbatan yard · 2025 · Onshore
Fabrication and welding, inspection and NDT, corrosion protection
312 t of piping and steelwork
Pick the service, the site and the length: the price with crew and equipment is worked out at once.