Neftchala district · Onshore
Drill cuttings treatment in Neftchala
Cuttings and oily water collected from the wells, treated on our pad, results checked by a lab
- Client
- An operator drilling onshore wells
- Period
- February 2024 – November 2024 (10 months)
- Most people on site in a day
- 19
- Man-hours
- 74,800
- Lost-time injuries
- 1

The brief
An operator drilling onshore needed a contractor to take drill cuttings and oily water from its wells and treat them.
In figures
- of drill cuttings treated
- 21,400t
- of oily water treated
- 38,000m³
- by vacuum tanker
- 2,650trips
How the work went
- Cuttings and fluids went from each well pad to our treatment pad by vacuum tanker.
- Cuttings and oily water were treated and the results checked by an accredited laboratory.
- Every trip was logged with a waybill and an acceptance note.
- There was one incident: a worker caught his hand in a pump cover and was off work for 9 days. Locking handles were fitted to the covers afterwards.
Result
21,400 t of cuttings and 38,000 m³ of oily water treated in 10 months.
Every trip had its paperwork, so the environmental inspection had no questions left.
The operator’s HSE manager
Services
Equipment used


Excavator · 23.2 t
Komatsu PC210LC-11
Lökbatan yard · ×2
- with operator
- ₼560 / day
- without operator
- ₼420 / day

Generator · 500 kVA
Caterpillar XQP500
Lökbatan yard · ×3
- with operator
- ₼520 / day
- without operator
- ₼380 / day
Other projects

Siyazan district · 2026 · Onshore
Flowline replacement in Siyazan
Pipelines, inspection and NDT, corrosion protection
18.4 km of 6 to 10-inch flowline replaced

Balakhani and Sabunchu fields · 2026 · Onshore
Workover campaign in Balakhani
Well services and workover
146 wells worked over

Sangachal · 2025 · Onshore
Pump skids built and set in Sangachal
Cranes and heavy lifting, fabrication and welding
3 skids fabricated and tested
Have similar work?
Pick the service, the site and the length: the price with crew and equipment is worked out at once.