Crews for a refinery shutdown

Welding, fitting, rigging and NDT crews worked two shifts for 36 days

Client
A refinery’s planned shutdown
Period
May 2021 – June 2021 (2 months)
Most people on site in a day
148
Man-hours
61,000
Lost-time injuries
0
A welder with a head torch working inside a vessel

The brief

A refinery needed welding, fitting, rigging and NDT crews on top of its own staff for a planned shutdown: 36 days on two shifts.

In figures

on site on the busiest day
148people
made
1,870welds
on two shifts
36days

How the work went

  • Certificates for all 148 people reached the refinery two weeks before the shutdown.
  • Crews worked under the refinery’s permit system, with our supervisors on every shift.
  • Our NDT crew tested welds on the same shift they were made.

Result

1,870 welds, 61,000 man-hours without a lost-time injury; the refinery restarted on schedule.

The client’s words
The paperwork was ready in advance, so the crews were at work from day one.

The refinery’s shutdown manager

Services

Equipment used

Other projects

Have similar work?

Pick the service, the site and the length: the price with crew and equipment is worked out at once.

Call usMessage on WhatsAppEquipment hireRequest a quote